Contents
This is our 84th post in the Infinity Hash Weekly Update series for Mar 10 2025.
This week we added no new miners. Mining profits for Infinity Hash went up a bit, with the price for IHS going down together with Bitcoin. We further improved the registration flow, started summer preparations at the farm, and resolved a major infrastructure maintenance task by replacing an old transformer with a new one while minimizing downtime.
You can always get a full overview of past charts and numbers on the Weekly Updates page.
Project Updates
Infinity Hash in Numbers
These are the numbers for week 10, 2025, from 2025-03-03 to 2025-03-09.
Metric | Current data | Change |
---|---|---|
Total Miners | 965 Miners | + 0 Miners |
Total Hashrate | 125.45 PH/s | + 0.69 PH/s |
Total IHS | 1,119,071 IHS | + 11,566 IHS |
IHS Price | $ 2.26 | – 18.15 % |
Rewards generated | 0.48377206 BTC | + 2.59 % |
Reinvested | 7,334 USDT | + 320 USDT |
Electricity paid | 28,338 USDT | + 781 USDT |
Dashboard and Feature Updates
This week, we added country selection to our registration flow, which enables us to:
- Only display supported payment methods to users (preventing frustration due to failed card and fiat payments).
- Reduce compliance risks for the project to uphold our long-term commitment to user privacy and ease of use.

Upon registration or your next login, you’ll see the country list pop-up in the dashboard. Should you have any questions or problems, feel free to contact us!
Miner and Farm Updates
Addendum: We forgot to mention 4 new Whatsminer M60S (total hash rate of 760 TH/s) from IHS sales that have been added on February 17th. The affected weekly update #82 was updated with the according table under Miner and Farm Updates.
Transformer repair and replacement
We detected problems with one of our older transformers (oil leakage and connectors overheating).
The transformer was now transported off-site for repairs and will be back in a few weeks. We also have an additional new transformer arriving on-site, so there will be no downtime because of this.
After first diagnosis, everything was prepared for the transport of the old transformer to the repair center, mainly making sure the crane and truck had proper access.
We timed the truck and crane to directly deliver the new transformer within the same transport to save costs and prevent any downtime for new miners arriving on site in the following weeks.
Links and Outlook
Infinity Hash Articles and Socials
This week you’ll find your Mining industry recap (Episode 25).
Mining Industry Recap, Episode 25
Weather Conditions
The current weather conditions at the mining farm are: Clear. Cold. Current temperatures at -11.72°C / 10.91°F provide excellent cooling conditions, with the weather forecast showing no changes in temperatures. This should result in stable profits.
Transparency
You can always check our pool and wallet links to get a complete and transparent overview of our pool, all miners in the pool, our public reinvest wallet, and our electricity costs on the page below:
Pool and wallet links
As always, it has been a pleasure to provide you with the latest information on the Infinity Hash project. We wish our community a great week and happy mining together!