This is our 84th post in the Infinity Hash Weekly Update series for Mar 10 2025.
This week we added no new miners. Mining profits for Infinity Hash went up a bit, with the price for IHS going down together with Bitcoin. We further improved the registration flow, started summer preparations at the farm, and resolved a major infrastructure maintenance task by replacing an old transformer with a new one while minimizing downtime.
Vous pouvez toujours consulter l’historique complet des graphiques et chiffres sur la page des Mises à Jour Hebdomadaires..
Mises à Jour du Projet
Infinity Hash en Chiffres
Voici les chiffres pour week 10, 2025, du 2025-03-03 au 2025-03-09.
Métrique | Données Actuelles | Changement |
---|---|---|
Nombre Total de Mineurs | 965 Miners | 0 mineur |
Puissance Totale (Hashrate) | 125.45 PH/s | + 0.69 PH/s |
Total des IHS | 1,119,071 IHS | + 11,566 IHS |
Prix de l’IHS | $ 2.26 | – 18.15 % |
Récompenses Générées | 0.48377206 BTC | + 2.59 % |
Réinvesti | 7,334 USDT | + 320 USDT |
Électricité Payée | 28,338 USDT | + 781 USDT |
Mises à Jour de l’Interface et des Fonctionnalités
This week, we added country selection to our registration flow, which enables us to:
- Only display supported payment methods to users (preventing frustration due to failed card and fiat payments).
- Reduce compliance risks for the project to uphold our long-term commitment to user privacy and ease of use.

Upon registration or your next login, you’ll see the country list pop-up in the dashboard. Should you have any questions or problems, feel free to contact us!
Mises à Jour des Mineurs et de l’Installation de Minage
Addendum: We forgot to mention 4 new Whatsminer M60S (total hash rate of 760 TH/s) from IHS sales that have been added on February 17th. The affected weekly update #82 was updated with the according table under Mises à Jour des Mineurs et de l’Installation de Minage.
Transformer repair and replacement
We detected problems with one of our older transformers (oil leakage and connectors overheating).
The transformer was now transported off-site for repairs and will be back in a few weeks. We also have an additional new transformer arriving on-site, so there will be no downtime because of this.
After first diagnosis, everything was prepared for the transport of the old transformer to the repair center, mainly making sure the crane and truck had proper access.
We timed the truck and crane to directly deliver the new transformer within the same transport to save costs and prevent any downtime for new miners arriving on site in the following weeks.
Liens et Perspectives
Articles et Réseaux d’Infinity Hash
This week you’ll find your Mining industry recap (Episode 25).
Mining Industry Recap, Episode 25
Conditions Météorologiques
Les conditions météorologiques actuelles sur le site de minage sont : Clear. Cold. Les températures actuelles de -11.72°C / 10.91°F provide excellent cooling conditions, with the weather forecast showing no changes in temperatures. This should result in stable profits.
Transparence
Vous pouvez toujours consulter nos liens de pool et de portefeuille pour obtenir une vue d'ensemble complète et transparente de notre pool, de tous les mineurs dans le pool, de notre portefeuille de réinvestissement public et de nos coûts d'électricité sur la page ci-dessous :
Liens des pools et des portefeuilles
Comme toujours, cela a été un plaisir de vous fournir les dernières informations sur le projet Infinity Hash. Nous souhaitons à notre communauté une excellente semaine et un bon minage ensemble !