This is our 84th post in the Infinity Hash Weekly Update series for Mar 10 2025.
This week we added no new miners. Mining profits for Infinity Hash went up a bit, with the price for IHS going down together with Bitcoin. We further improved the registration flow, started summer preparations at the farm, and resolved a major infrastructure maintenance task by replacing an old transformer with a new one while minimizing downtime.
يمكنك دائمًا الحصول على نظرة شاملة للرسوم البيانية والأرقام السابقة على صفحة التحديثات الأسبوعية.
تحديثات المشروع
إنفينيتي هاش بالأرقام
فيما يلي الأرقام المتعلقة بـ week 10, 2025ابتداءً من 2025-03-03 حتى 2025-03-09.
بيانات قياسية | البيانات الفعلية | تغييرات |
---|---|---|
العدد الكلي لاجهزة التعدين | 965 Miners | لا زيادة في المعدنين |
الإجمالي الكلي لمعدل الهاش | 125.45 PH/s | + 0.69 PH/s |
إجمالي عدد الحصص | 1,119,071 IHS | + 11,566 IHS |
قيمة IHS | $ 2.26 | – 18.15 % |
المكافآت الناتجة | 0.48377206 BTC | + 2.59 % |
إعادة الاستثمار | 7,334 USDT | + 320 USDT |
تكاليف الكهرباء المدفوعة | 28,338 USDT | + 781 USDT |
تحديثات لوحة المعلومات والخصائص
This week, we added country selection to our registration flow, which enables us to:
- Only display supported payment methods to users (preventing frustration due to failed card and fiat payments).
- Reduce compliance risks for the project to uphold our long-term commitment to user privacy and ease of use.

Upon registration or your next login, you’ll see the country list pop-up in the dashboard. Should you have any questions or problems, feel free to contact us!
تحديثات اجهزة التعدين والمزارع
Addendum: We forgot to mention 4 new Whatsminer M60S (total hash rate of 760 TH/s) from IHS sales that have been added on February 17th. The affected weekly update #82 was updated with the according table under تحديثات اجهزة التعدين والمزارع.
Transformer repair and replacement
We detected problems with one of our older transformers (oil leakage and connectors overheating).
The transformer was now transported off-site for repairs and will be back in a few weeks. We also have an additional new transformer arriving on-site, so there will be no downtime because of this.
After first diagnosis, everything was prepared for the transport of the old transformer to the repair center, mainly making sure the crane and truck had proper access.
We timed the truck and crane to directly deliver the new transformer within the same transport to save costs and prevent any downtime for new miners arriving on site in the following weeks.
روابط ومؤشرات مستقبلية
مقالات إنفينيتي هاش ووسائل التواصل الاجتماعي
This week you’ll find your Mining industry recap (Episode 25).
Mining Industry Recap, Episode 25
أوضاع الأحوال الجوية
حالة الطقس الحالية في مزرعة التعدين هي: Clear. Cold. درجات الحرارة الحالية في -11.72°C / 10.91°F provide excellent cooling conditions, with the weather forecast showing no changes in temperatures. This should result in stable profits.
الشفافية
يمكنك دائماً التحقق من روابط المجمع والمحفظة للحصول على نظرة كاملة وشفافة عن مجمعنا، جميع اجهزة التعدين في المجمع، محفظة إعادة الاستثمار العامة، وتكاليف الكهرباء الخاصة بنا في الصفحة أدناه
روابط تجمعات التعدين والمحافظ
كما هو الحال دائماً، يشرفنا أن نقدم لكم أحدث المعلومات حول مشروع أنفينيتي هاش. نتمنى لمجتمعنا أسبوعاً سعيداً وتعديناً ممتعاً معاً